Failure Scenarios for Contingency Planning

Dependency

Failure Scenario Duration

Problem Probability

Infrastructure Supplier Local Water Supply Outage 1 day

2

Infrastructure Supplier Local Water Supply Outage 2-3 days

2

Infrastructure Supplier Local Water Supply Outage > 3 days

1

Infrastructure Supplier Local Water Supply Contamination 1 day

3

Infrastructure Supplier Local Water Supply Contamination 2-3 days

2

Infrastructure Supplier Local Water Supply Contamination > 3 days

1

Infrastructure Supplier Local Power Outage 1 day

2

Infrastructure Supplier Local Power Outage 2-3 days

1

Infrastructure Supplier Local Power Outage > 3 days

1

Infrastructure Supplier Waste Disposal Stoppage 3 days

3

Infrastructure Supplier Waste Disposal Stoppage 3-7 days

2

Infrastructure Supplier Waste Disposal Stoppage > 7 days

1

Infrastructure Supplier Sewage Processing & Treatment Failure 1 day

3

Infrastructure Supplier Sewage Processing & Treatment Failure 1-3 days

2

Infrastructure Supplier Sewage Processing & Treatment Failure > 3 days

1

Infrastructure Supplier Natural Gas Outage 1 day

1

Infrastructure Supplier Natural Gas Outage 2-3 days

1

Infrastructure Supplier Natural Gas Outage > 3 days

1

Infrastructure Supplier Remote Power Outage – Regional or International 1 day

5

Infrastructure Supplier Remote Power Outage - Regional or International 2-3 days

4

Infrastructure Supplier Remote Power Outage - Regional or International > 3 days

3

Infrastructure Supplier Failure of Local Emergency Services 1 day

3

Infrastructure Supplier Failure of Local Emergency Services 2-3 days

2

Infrastructure Supplier Failure of Local Emergency Services > 3 days

1

Infrastructure Supplier External Communications System Failure 1 day

3

Infrastructure Supplier External Communications System Failure 1-3 days

2

Infrastructure Supplier External Communications System Failure > 3 days

1

Supplier Fuel Rationing / Significant Price Increase Up to 1 month

5

Supplier Fuel Rationing / Significant Price Increase 2-3 month

5

Supplier Fuel Rationing / Significant Price Increase > 3 month

4

Supplier Critical Part / Product Supplier Outage 1 day

4

Supplier Critical Part / Product Supplier Outage 2-5 days

3

Supplier Critical Part / Product Supplier Outage > 5 days

2

Supplier Multi-tier Supply Chain Failure 1-3 day

4

Supplier Multi-tier Supply Chain Failure 3-7 days

3

Supplier Multi-tier Supply Chain Failure > 7 days

2

Supplier Raw Materials Stoppage / Shortage 1-3 day

4

Supplier Raw Materials Stoppage / Shortage 3-7 days

3

Supplier Raw Materials Stoppage / Shortage > 7 days

2

Supplier Customs Import Slowdown 0-2 weeks

4

Supplier Customs Import Slowdown 2-4 weeks

3

Supplier Customs Import Slowdown > 4 weeks

2

Supplier Customs Export Slowdown 0-2 weeks

4

Supplier Customs Export Slowdown 2-4 weeks

3

Supplier Customs Export Slowdown > 4 weeks

2

Supplier Multiple Non-Critical Supplier Outages 0-2 weeks

3

Supplier Multiple Non-Critical Supplier Outages 2-4 weeks

2

Supplier Multiple Non-Critical Supplier Outages > 4 weeks

1

Supplier Transportation / Shipping Distribution Slow Down 1 week

5

Supplier Transportation / Shipping Distribution Slow Down 1-2 weeks

4

Supplier Transportation / Shipping Distribution Slow Down > 2 weeks

3

Facilities Security System / Access Failure 1 day

3

Facilities Security System / Access Failure > 1 day

2

Facilities Generator Failure at Headquarters 1 day

4

Facilities Generator Failure at Headquarters 2-7 days

3

Facilities Generator Failure at Headquarters > 7 days

1

Facilities Punch Card / Clock System Failure 1 day

3

Facilities Punch Card / Clock System Failure > 1 day

2

Facilities Internal Communications System Failure 1 day

2

Facilities Internal Communications System Failure > 1 day

1

Product Product Shortages Due to Stockpiling 1 month

4

Product Product Shortages Due to Stockpiling > 1 month

3

Product Warranty Product Problem Requiring Engineering / Manufacturing Change 1 month

3

Product Warranty Product Problem Requiring Engineering / Manufacturing Change > 1 month

1

Product Non-Warranty Product Problem Requiring Engineering / Manufacturing Change 1 month

2

Product Non-Warranty Product Problem Requiring Engineering / Manufacturing Change > 1 month

1

Customer Inability to Finance Acquisition of Products 30 days

4

Customer Inability to Finance Acquisition of Products 30-90 days

3

Customer Inability to Finance Acquisition of Products > 90 days

2

Customer Inability to Meet Payable Schedule 30 days

4

Customer Inability to Meet Payable Schedule 30-90 days

3

Customer Inability to Meet Payable Schedule > 90 days

2

Customer Inability to Communicate with Customer 1-7 days

3

Customer Inability to Communicate with Customer > 7 days

2

System / equipment Critical Shop Floor Machine Fails 1 day

2

System / equipment Critical Shop Floor Machine Fails > 1 days

1

Systems Order System Failure 1-2 days

2

Systems Order System Failure > 2 days

1

Systems Inventory Systems Failure 1-2 days

2

Systems Inventory Systems Failure > 2 days

1

Systems Accounting Systems Failure 1-2 days

2

Systems Accounting Systems Failure > 2 days

1

Systems H/R Systems Failure 1-2 days

2

Systems H/R Systems Failure > 2 days

1

Systems Customer Management Systems Failure 1-2 days

2

Systems Customer Management Systems Failure > 2 days

1

Systems Corporate Email Outages 1 day

1

Systems Corporate Email Outages 2-3 days

1

Systems Corporate Email Outages > 3 days

1

Systems LAN Outage < 2 days

1

Systems LAN Outage Up to 1 wk

1

Systems LAN Outage > 1 wk

1

Systems WAN Outage < 2 days

2

Systems WAN Outage Up to 1 wk

1

Systems WAN Outage > 1 wk

1

Systems External Internet Email Outages 1 day

4

Systems External Internet Email Outages 2-3 days

4

Systems External Internet Email Outages > 3 days

4

Systems Digital Phone System / Voice Mail Failure 1 day

4

Systems Digital Phone System / Voice Mail Failure > 1 day

3

Systems Local Phone / Fax Outages 1 day

1

Systems Local Phone / Fax Outages 2-3 days

1

Systems Local Phone / Fax Outages > 3 days

1

Systems Remote Phone / Fax Outages 1 day

4

Systems Remote Phone / Fax Outages 2-3 days

4

Systems Remote Phone / Fax Outages > 3 days

3

Systems Remote Phone / Fax Outages Impacting Suppliers 2-3 days

4

Systems Remote Phone / Fax Outages Impacting Suppliers > 3 days

3

Interface Data Collection Failures 1 day

4

Interface Data Collection Failures 2-3 days

4

Interface Total Data Interface Stoppage 1-2 days

3

Interface Total Data Interface Stoppage > 2 days

2

Interface Data Corruption to Critical Business Applications Up to 1 week

3

Interface Data Corruption to Critical Business Applications > 1 week

2

Interface Data Corruption to Critical Business Applications < 2 days

3

Interface Data Corruption to Customer / Partner Systems Up to 1 week

2

Interface Data Corruption to Customer / Partner Systems > 1 week

2

Interface Data Corruption to Customer / Partner Systems < 2 days

2

Employee Employees Cannot Get to Work 1 day

3

Employee Employees Cannot Get to Work 2-3 days

2

Employee Employees Cannot Get to Work > 3 days

1

Employee Employee Must Stay Home (childcare, food, power, etc.) 1 day

3

Employee Employee Must Stay Home (childcare, food, power, etc.) 2-3 days

2

Employee Employee Must Stay Home (childcare, food, power, etc.) > 3 days

1

 

Send mail to webmaster@systemtransformation.com with questions or comments about this web site. 
Trouble printing this page? Click here for printing instructions.
Copyright © 1999 - 2008 Tactical Strategy Group, Inc. Last modified: May 21, 2008