The Program Office can supply you with an MS Project template with these
tasks defined.
TASK |
END DATE |
I. Organization
|
|
| Review Contingency Planning strategy. |
|
| Identify Executive management team. |
|
| Identify high-level business functions. |
|
| Assign team to each business function. |
|
| Incorporate contingency planning into existing
management activities. |
|
| Develop project plan for contingency planning efforts. |
|
| Report organization and project plans to Project
Office. |
|
| Milestone Deliverables: Business Functions Defined,
Contingency Team(s) Defined and An Initial Contingency Project Plan |
|
II. Preparation
|
|
| Attend Contingency Planning Workshop. |
|
| Review workshop materials. |
|
| Meet with Business Leaders to discuss their expectations
and constraints. |
|
| Review White Paper |
|
| Meet with Functional Leaders |
|
| Identify systems, electronic interfaces, embedded
technologies, facilities, and third parties. |
|
| Identify key individuals and organizations involved
with project. |
|
| Identify constraints |
|
| Identify reports, databases or persons with valuable
knowledge. |
|
| Identify business processes that other business functions
depend upon. |
|
| Identify business processes with non-Year risks and
contingency plans. |
|
| Identify business processes with established
non-project
Crisis Management Teams and procedures. |
|
| Review availability of resources for contingency planning
project. |
|
| Review progress of external contingency planning projects. |
|
| Resolve critical deficiencies, issues and concerns. |
|
| Milestone Deliverables: Business Processes defined for each
Business Function |
|
TASK |
END DATE |
III. Business Risk Analysis
|
|
| Conduct risk assessment for each business function. |
|
| Eliminate non-critical business processes from project. |
|
| List and prioritize critical business processes. |
|
| Revise project tasks to reflect new priorities. |
|
| Manage identified risks. |
|
| Milestone Deliverables: A Business Processes Risk
Assessment, An updated project plan with tasks to develop contingency plans for each
business function |
|
IV. Contingency Planning
|
|
| Assess existing contingency plans for applicability to
risks. |
|
| Develop outline of each contingency plan and action within
project. |
|
| Propose, prioritize and obtain approval for each new
contingency plan and action. |
|
| Build and document new contingency plans and actions. |
|
| Track, implement and retract contingency plans and actions.
|
|
| Milestone Deliverables: A fully documented set of
contingency plans for each business function. |
|
V. Crisis Management Planning
|
|
| Assess and adapt as necessary existing Crisis Management
Team plans. |
|
| Propose, prioritize, and obtain approval for each new Crisis Management Team. |
|
| Build, organize, and document new Crisis
Management Teams. |
|
| Communicate existing and new escalation procedures. |
|
| Milestone Deliverables: A fully documented set of
Crisis Management Teams for each business function. |
|
VI. Contingency Planning/Crisis Management
Teams
|
|
| Monitor daily business function activities. |
|
| Revise, document, and properly communicate contingency
plans, Crisis Management Teams, and procedures. |
|
| Milestone Deliverables: Regular status report to monitor
your contingency planning project progress, concerns, and issues. When necessary, updated
contingency plans. |
|